April 1st: Try out many sketches, decide on final shape

April 5th: Brainstorm materials and how it will be manufactured.

April 7th: Order materials (2 week lead time)

April 14th: Finalize CAD Drawings

April 21st: Receive materials

April 24th: Start machining

Present final on May 1st

 

 

3 Comments. Leave new

  • Matthew Clark
    May 10, 2017 4:53 pm

    Looks like a have a good plan to combat these last steps in your project. Since you may run into problems while machining, I would suggest you start earlier in the machine phase.

    Reply
  • Jimmy Speedy
    May 10, 2017 12:22 pm

    Sounds like you’ve got a solid amount of work ahead of you. Having it all planned out as you do will definitely help the process and product quality. Hope everything goes smoothly, good luck with the project!

    Reply
  • You have a lot to get done. It would be nice to see time estimates on how long each task will take in order to organize your schedule around

    Reply